VMware Cloud Foundation (VCF) 9.1 Bring-Up: Step-by-Step Deployment Guide

viquarmca
4 minutes ago
4 min read

Deploying VMware Cloud Foundation (VCF) 9.1 introduces a streamlined, fleet-centric architecture. Gone is the legacy Cloud Builder appliance and its rigid Excel parameter workbook. Instead, VCF 9.1 uses the unified VCF Installer appliance, which validates prerequisites as hard gates, pulls binaries directly from an online or offline depot, stands up VCF Operations, VCF Automation, VCF Management Services (VCFMS), vCenter, and NSX Manager, and finally converts itself into the SDDC Manager.


This guide walks through a greenfield VCF 9.1 bring-up from pre-flight preparation to post-deployment verification, highlighting real-world field gotchas along the way.


Phase 1: Pre-Deployment Planning & Infrastructure Prerequisites

The VCF 9.1 Installer enforces pre-checks as strict gates—if DNS, NTP, certificates, or network MTU values are misaligned, bring-up will halt before deploying a single appliance.


1. Network & VLAN Architecture

Plan your VLANs, subnets, and IP pools before touching the installer. For vSAN ESA and NSX Overlay traffic, configure MTU 9000 (Jumbo Frames) end-to-end across your physical Top-of-Rack (ToR) switches


2. DNS & NTP Verification

  • DNS (Forward & Reverse): Every single FQDN—ESXi hosts, VCF Installer, SDDC Manager, vCenter, NSX Manager Cluster VIP + 3 appliances, VCF Operations, and VCFMS—must have both A and PTR records created it should all be in small letters and resolvable from outside the target cluster.

  • NTP: Configure a reliable external NTP source reachable by all ESXi hosts and the VCF Installer appliance. Clock skew across nodes will break SSO and certificate validation.


3. ESX Host Baseline Preparation

  1. Install ESXi 9.1 (or supported 9.x build) on each management domain host (minimum 4 hosts for production vSAN ESA; 3 hosts supported for consolidated labs with capacity warning acknowledgment).

  2. Configure the static Management IP, subnet mask, gateway, DNS servers, and hostname FQDN via DCUI.

  3. Enable SSH and configure NTP to start and stop with the host.

  4. SSL Certificate Check: Verify that each ESXi host's self-signed SSL certificate Subject Alternative Name (SAN) matches its configured FQDN. If you renamed the host after installation, regenerate the certificate (/sbin/generate-certificates) and restart hostd and vpxa so the installer doesn't reject a hostname/SSL key mismatch.

  5. Single Uplink Rule: Keep only one physical NIC (vmnic0) attached to vSwitch0 during initial prep. Leave secondary NICs (vmnic1, etc.) unassigned so the VCF Installer can cleanly migrate them to the new VDS.


Phase 2: Deploy the VCF Installer & Configure the Depot

  1. Deploy the VCF Installer OVA: On a jump host or existing management infrastructure outside the target cluster, deploy the VCF 9.1 Installer OVA. Assign its static IP, netmask, gateway, DNS, NTP, and root/admin credentials.

  2. Access the UI: Open https://<vcf-installer-fqdn> in your browser and log in as admin@local

  3. Configure Depot & Binary Management:

    • Navigate to Depot Settings and choose either Online Depot (using your Broadcom Support Portal Software Depot ID and one-time Activation Code) or Offline Depot (if staging bundles via the VCF Download Tool in an air-gapped environment).

    • Open Binary Management, select VCF 9.1.0.0, and download the required installation bundles (ESX, vCenter, NSX, VCF Operations, VCF Automation, and SDDC Manager). In my case we are sing online depot connection which can be seen in the below .



Phase 3: Walk Through the VCF 9.1 Bring-Up Wizard


Click Get Started on the home screen to launch the four-stage guided wizard (Introduction → Depot → Prepare → Deploy):



Stage 1 – Deployment Path: Select Deploy a New VCF Fleet. Choose your sizing topology (High Availability / Production vs. Simple / Lab).




Stage 2 – Existing Component Information:

  • We select i have an Existing VCF Automation or i will deploy later as my customer wants this to be done later as day 2 .


  • We select size option for our deployment model as per the Desing mention in PNP work book.


  • We select our Network option as per our design we are going with use a seperate dedicate network for VM traffic and VCF management network we are use VM management network traffic. Coming to NSX consumption we decided at this point to go with distributed connectivity



  • We select Storage for my design its going to VMFS on Fibre Channel (FC)


  • Review Prerequisites and click Next


Stage 2 – General Information:

  • Select Version 9.1.0.0.

  • Enter the VCF Instance Name, Management Domain Name, DNS Servers, NTP Servers, and Default DNS Domain Suffix. and Click Next


Stage 3 – Hosts & Fingerprints:

  • Add each ESXi host FQDN and root password.

  • Click Confirm All Fingerprints to verify and trust each host's SSL thumbprint. and Click Next



  • Post Validate Click on Yes to Proceed


Stage 4 – Networks:

  • Map VLAN IDs, Subnets, Gateways, MTU values, and IP Ranges for ESX Management,VM Management , vMotion, vSAN, NSX Overlay, and the VCF Management Services (VCFMS) IP Pool, and Click Next



Stage 5 – VCF Management Components:

  • Review and confirm the auto-populated FQDNs for VCF Operations, Cloud Proxy, VCF Management Services (Fleet LCM, Identity Broker, Services Runtime), and VCF Automation.(if we are deploying ). Click Next

Stage 6 – vCenter & Storage:

  • Enter the vCenter FQDN, Datacenter Name, Cluster Name, and SSO Domain (vsphere.local). Click Next

  • Storage is VMFS on Fibre Channel(FC) and define the datastore name which is been created


Stage 7 – Distributed Switch (VDS):

  • Name your VDS, confirm MTU (9000 or 1500 per your physical fabric), and map your physical NICs (vmnic0 / vmnic1) to uplink1 and uplink2.


Stage 8 – NSX Manager & SDDC Manager:

  • Provide the NSX Manager Cluster VIP FQDN and the 3 NSX Manager Appliance FQDNs. and VPC Gateway Connecitivty Details

  • Confirm the SDDC Manager FQDN and set its administrator credentials (remember: the VCF Installer appliance converts into SDDC Manager at the end of the workflow)


Phase 4: Validate, Export JSON Spec & Deploy


  1. Download the JSON Specification: On the Review screen, click Download JSON Spec. Store this file in your engineering runbook—it is invaluable for disaster recovery documentation or automated re-runs.


  1. Click on Next and Click Deploy this will start the validation , if anything is not right like DNS or netowrk u might get and error here fix that issue and then click again retry . In this use case all was fine we deployed it sucessfully.

  1. on the left side you can view all the password and fqdns for the each compoents


Post-Deployment Verification we will cover in the next blog untill then happy learning.